Activity list
rozpocznij naukę
The primary output of breaking down the WBS work packages.
Alternative analysis
rozpocznij naukę
The identification of more than one solution. Consider roles, materials, tools, and approaches to the project work.
Control threshold
rozpocznij naukę
A predetermined range of acceptable variances, such as +/–10 percent off schedule. Should the variance exceed the threshold, then project control processes and corrected actions will be enacted.
Critical path
rozpocznij naukę
"The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. There can be more than one critical path.
Activities in the critical path have no float."
rozpocznij naukę
Activities in the critical path have no float. "
Early finish
rozpocznij naukę
The earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float.
Early start
rozpocznij naukę
The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float.
External dependencies
rozpocznij naukę
As the name implies, these are dependencies outside of the project’s control. Examples include the delivery of equipment from a vendor, the deliverable of another project, or the decision of a committee, lawsuit, or expected new law.
Finish-to-finish
rozpocznij naukę
An activity relationship type that requires the current activity to be finished before its successor can finish.
Finish-to-start
rozpocznij naukę
An activity relationship type that requires the current activity to be finished before its successor can start.
Fragnet
rozpocznij naukę
A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Also called a subnet.
Free float
rozpocznij naukę
This is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities.
Hard logic
rozpocznij naukę
Logic that describes activities that must happen in a particular order. For example, the dirt must be excavated before the foundation can be built. The foundation must be in place before the framing can begin. Also known as a mandatory dependency.
Internal dependencies
rozpocznij naukę
Internal relationships to the project or the organization. For example, the project team must create the software as part of the project’s deliverable before the software can be tested for quality control.
Lag time
rozpocznij naukę
Positive time that moves two or more activities further apart.
Late finish
rozpocznij naukę
The latest a project activity can finish. Used in the backward pass procedure to discover the critical path and the project float.
Late start
rozpocznij naukę
The latest a project activity can begin. Used in the backward pass procedure to discover the critical path and the project float.
Lead time
rozpocznij naukę
Negative time that allows two or more activities to overlap where ordinarily these activities would be sequential.
Management reserve
rozpocznij naukę
A percentage of the project duration to combat Parkinson’s Law. When project activities become late, their lateness is subtracted from the management reserve.
Mandatory dependencies
rozpocznij naukę
These dependencies are the natural order of activities. For example, you can’t begin building your house until your foundation is in place. These relationships are called hard logic.
Parametric estimate
rozpocznij naukę
A quantitatively based duration estimate that uses mathematical formulas to predict how long an activity will take based on the quantities of work to be completed.
Parkinson’s Law
rozpocznij naukę
A theory that states: “Work expands so as to fill the time available for its completion.” It is considered with time estimating, because bloated or padded activity estimates will fill the amount of time allotted to the activity.
Planning package
rozpocznij naukę
A WBS entry located below a control account and above the work packages. A planning package signifies that there is more planning that needs to be completed for this specific deliverable.
Precedence diagramming method
rozpocznij naukę
A network diagram that shows activities in nodes and the relationship between each activity. Predecessors come before the current activity, and successors come after the current activity.
Project calendars
rozpocznij naukę
Calendars that identify when the project work will occur.
Project float
rozpocznij naukę
This is the total time the project can be delayed without passing the customer- expected completion date.
Project network diagram
rozpocznij naukę
A diagram that visualizes the flow of the project activities and their relationships to other project activities.
Refinement
rozpocznij naukę
An update to the work breakdown structure.
Resource calendars
rozpocznij naukę
Calendars that identify when project resources are available for the project work.
Resource-leveling heuristic
rozpocznij naukę
A method to flatten the schedule when resources are overallocated. Resource leveling can be applied using different methods to accomplish different goals. One of the most common methods is to ensure that workers are not overextended on activities.
Rolling wave planning
rozpocznij naukę
The imminent work is planned in detail, while the work in the future is planned at a high level. This is a form of progressive elaboration.
Schedule management plan
rozpocznij naukę
A subsidiary plan in the project management plan. It defines how the project schedule will be created, estimated, controlled, and managed.
Start-to-finish
rozpocznij naukę
An activity relationship that requires an activity to start so that its successor can finish. This is the most unusual of all the activity relationship types.
Start-to-start
rozpocznij naukę
An activity relationship type that requires the current activity to start before its successor can start.
Subnet
rozpocznij naukę
A representation of a project network diagram that is often used for outsourced portions of projects, repetitive work within a project, or a subproject. Also called a fragnet.
Template
rozpocznij naukę
A previous project that can be adapted for the current project and forms that are pre-populated with organizational-specific information.
Three-point estimate
rozpocznij naukę
"An estimating technique for each activity that requires optimistic, most likely, and pessimistic estimates to be created.
Based on these three estimates, an average can be created to predict how long the activity should take."
rozpocznij naukę
Based on these three estimates, an average can be created to predict how long the activity should take. "
Work package
rozpocznij naukę
The smallest item in the work breakdown structure.